Indonesia and China have agreed on spending an additional $1.2bn for the high-speed railway project in Indonesia, reported Reuters citing an Indonesian government official.
PT KCIC, a consortium comprising Indonesian and Chinese state companies that are building the railway, earlier expected the project to be $2bn over budget, increasing the overall expenditure to $7.36bn.
Indonesia state-owned enterprises deputy minister Kartika Wirjoatmodjo was quoted by the news agency as saying: “We agreed on the cost overrun figure of $1.2bn.
“There are several items that they are still reviewing regarding taxes and frequency clearing fees, but we have agreed on the numbers.”
He also stated that more details, including a further loan from the China Development Bank to meet the extra costs, will be finalised in a month.
Firms included in the consortium were anticipated to raise their equity interest.
How well do you really know your competitors?
Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.
Thank you!
Your download email will arrive shortly
Not ready to buy yet? Download a free sample
We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form
By GlobalDataIndonesia’s state-run rail operator PT KAI secured $210m from the government last month to support the completion of the project.
PT KAI, along with state-owned construction company Wijaya Karya, has a 60% stake in KCIC.
Designed to connect Jakarta with Bandung, the 142km project contract was won by KCIC in 2015.
Claimed to be the first high-speed rail project in Indonesia, the project is anticipated to conclude in June 2023 after facing delays due to the pandemic.