Network Rail has completely reopened Waterloo station in the UK following a series of complex upgrade works that lasted for nearly three and a half weeks.

The modernisation works form part of the £800m Waterloo and South West Upgrade, which included the extension of platforms one to four in order to accommodate longer ten-car trains.

The programme is expected to increase overall capacity at the station by 30% by December next year and support additional 45,000 passengers during peak hours.

Waterloo station faced some initial disruptions following the reopening, as signalling testing took slightly longer than originally anticipated.

Network Rail route managing director Becky Lumlock said: “The work we have completed in three and a half weeks this August will benefit passengers for decades to come.

“The longer platforms will create space for longer trains, making journeys more comfortable for passengers, particularly at the busiest times of day.”

How well do you really know your competitors?

Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.

Company Profile – free sample

Thank you!

Your download email will arrive shortly

Not ready to buy yet? Download a free sample

We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form

By GlobalData
Visit our Privacy Policy for more information about our services, how we may use, process and share your personal data, including information of your rights in respect of your personal data and how you can unsubscribe from future marketing communications. Our services are intended for corporate subscribers and you warrant that the email address submitted is your corporate email address.

The modernisation programme began on 5 August and involved a team of 1,000 personnel.

"The longer platforms will create space for longer trains, making journeys more comfortable for passengers, particularly at the busiest times of day."

The development included the laying of 1,270m of track, in addition to the installation of 230m of pre-cast concrete.

Other works such as the construction of 160m of new platform space and laying seven miles of cable were also carried out during the refurbishment.

Lumlock added: “Over the next 16 months we’ll turn our attention to the final stages of the redevelopment of the former International Terminal.”

Network Rail is responsible for managing and developing the UK’s rail infrastructure, includes 20,000mi of track, 40,000 bridges and viaducts, signals, level crossings and stations.


Image: London Waterloo – Day 1 v Day 23. Photo: courtesy of Network Rail.