UK rail infrastructure manager Network Rail (NR) has started excavation work as part of its project to build the new Ordsall Chord between Manchester Victoria and Piccadilly stations.

The work will be carried out between Trinity Way and the River Irwell as the foundations for the Chord.

According to NR, works have been planned to cause the least possible disruption, with all four lanes of Trinity Way remaining open and will have a 20mph speed restriction on the ring road for safety reasons.

The project is a major component of the £600m Northern Hub programme, which will allow the operation of 700 more trains a day in northern England.

The Ordsall Chord is being built as part of NR’s £1bn improvements planned across the north of England under the Railway Upgrade Plan.

"The creation of the Ordsall Chord will bring many benefits to the city and the north of England."

Following completion next year, the Ordsall Chord will deliver a more reliable, faster and efficient railway to the millions of passengers who travel by train every year.

How well do you really know your competitors?

Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.

Company Profile – free sample

Thank you!

Your download email will arrive shortly

Not ready to buy yet? Download a free sample

We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form

By GlobalData
Visit our Privacy Policy for more information about our services, how we may use, process and share your personal data, including information of your rights in respect of your personal data and how you can unsubscribe from future marketing communications. Our services are intended for corporate subscribers and you warrant that the email address submitted is your corporate email address.

Network Rail route delivery director Nick Spall said: "The road will remain open as much as possible, but to allow cranes and equipment to be moved safely across Trinity Way, there may be a need for overnight closures but motorists will be given advanced warning.

"The creation of the Ordsall Chord will bring many benefits to the city and the north of England. Not only will it link the major stations within Manchester but will help support delivery of faster trains linking Manchester Victoria and Liverpool, as well as improving journey times to Liverpool, Leeds and the north-east."

The works will be carried out as part of a joint effort between Network Rail, Transport for Greater Manchester (TfGM), in addition to Manchester and Salford city councils.

TfGM chair Andrew Fender said: "The Ordsall Chord project, which will incorporate a major redevelopment of Salford Central, is a significant programme of works that, along with the rest of the North of England Programme, will revolutionise rail travel throughout our region.

"I want to reassure commuters and local residents that TfGM has been, and will continue, to work closely with Network Rail and Manchester and Salford City Council to minimise disruption along Trinity Way and surrounding areas, and maintaining four lanes to traffic for the duration of the project should go some way to ensuring that."

The project was previously challenged by former president of the Institute of Civil Engineers Mark Whitby on two statutory grounds of the Transport and Works Act order, one of the Listed Building Consent and a judicial review of the planning permission.

Last October, NR secured approval to build the £85m Ordsall Chord rail link, after a judge dismissed a legal challenge to the project.

It is reported that the next appeal hearing related to the stalled legal challenge against the Chord is scheduled to be heard by 4 March.


Image: The Ordsall Chord project is scheduled to be completed in 2017. Photo: courtesy of Network Rail.